Project Overview

PLP Stone is a newly developed storage and distribution facility featuring a large, open-plan office environment. The 345,000 sq ft warehouse boasts an impressive 18-metre clear internal height and has achieved both an EPC A rating and a BREEAM Excellent certification.

Bion delivered the complete electrical installation package for the project, supporting the building’s high-performance and sustainability objectives.

Customer: Davis & Birch/ Glencar

Project: New Build industrial unit and office installation

Valuation: £700k

Sector: Industrial & Logistics

Scope of Works

Main Incoming Supply

Full electrical installation from the main incoming supply through to a purpose-built LV distribution panel, forming the backbone of the project’s power infrastructure.

Power Distribution

Installation and distribution of power to all distribution boards, providing reliable supply across the entire facility.

Building & Equipment Services

Electrical supplies installed for lighting, small power, EV charging points, roller shutter doors, and all mechanical equipment.

Fire Alarm, Testing & Commissioning

Complete fire alarm system installation, followed by full testing and commissioning to ensure compliance, safety, and operational performance.

Challenges Presented

Delivering such a large-scale electrical package across a vast site required close coordination with multiple trades to ensure works progressed efficiently and without disruption. Maintaining momentum while meeting a fixed and demanding programme was a key challenge—one that was successfully achieved with the project delivered on schedule.

    Solutions Implemented

    Regular coordination was key to the smooth delivery of this project. Weekly main contractor meetings, alongside daily site team briefings, allowed us to proactively address issues and maintain a seamless workflow between trades. Potential challenges were often resolved before they could impact progress. Additionally, Gantt charts were implemented and regularly updated to track progress, manage dependencies, and keep the project on schedule.

    The project was completed ahead of schedule, with all works delivered to an exceptionally high standard. Upon handover, all certificates, documentation, and commissioning records were provided, ensuring full compliance and client satisfaction.