Project Overview
Bion Electrical was appointed to deliver the electrical and mechanical refurbishment works for a major hotel upgrade project involving the refurbishment of guest bedrooms and public areas. Working alongside Murray & Willis Ltd
, the project formed part of a wider hospitality improvement programme focused on enhancing guest experience, modernising services, and improving the overall operational efficiency of the hotel environment.
Customer: Murray & Willis
Project: Bedroom and Lobby Refurbs
Valuation: £900,000
Sector: Hospitality
Scope of Works
Electrical Design & Planning
Development of a full electrical design tailored to the client’s requirements, ensuring the system layout and infrastructure supported both current needs and future expansion.
Strip-Out & Infrastructure Installation
Complete removal of existing services, followed by the installation of new containment systems for power, lighting, data, and fire/security throughout the building.
Plant Room & Service Distribution
Creation of a dedicated plant room to house distribution boards and mechanical plant, with power and services distributed across consultation rooms, offices, and associated spaces.
Testing, Commissioning & Handover
Comprehensive testing and commissioning of all installed systems, followed by a full client demonstration to confirm operational performance and project completion.
Challenges Presented
- Delivering refurbishment works within a live hotel environment while maintaining uninterrupted guest services.
- Coordinating phased works across occupied and operational areas of the building.
- Upgrading existing electrical and mechanical systems within confined ceiling and service spaces.
- Managing tight programme deadlines to ensure room availability and operational continuity.
- Integrating modern energy-efficient systems into existing infrastructure without major structural disruption.
- Maintaining strict health, safety, and noise control procedures throughout the refurbishment programme.
Solutions Implemented
Carefully phased delivery strategy to minimise disruption to hotel operations and ensure efficient progression across all refurbishment areas. Close coordination with the principal contractor and hotel management team enabled works to be scheduled around occupancy levels and operational requirements.
Energy-efficient LED lighting systems were introduced throughout the refurbished bedrooms and public spaces, improving both aesthetics and operational performance while reducing long-term energy consumption. Mechanical and electrical services were upgraded to provide improved reliability, occupant comfort, and compliance with modern hospitality standards.
The team utilised flexible working arrangements and detailed programme coordination to maintain progress within the live environment while ensuring all installations met the required quality and safety standards.