Project Overview
Jungheinrich involved the refurbishment of their existing headquarters in Milton Keynes, creating two floors of high-end office space alongside a warehouse training centre. The project achieved a BREEAM Excellent rating and was fitted with state-of-the-art LED lighting and control systems throughout. All services were installed fully on display, showcasing meticulous workmanship and resulting in a visually impressive and technically sophisticated installation.
Customer: Davis & Birch/ Glencar
Project: Head Office build and Fitout
Valuation: £1m
Sector: Offices & Warehousing
Scope of Works
Complete Strip-Out
Full removal of the existing electrical infrastructure and services throughout the building, preparing the site for a complete modern fit-out.
Power & Distribution
Installation of a new LV panel and comprehensive distribution network to supply small power, lighting, and all mechanical and ventilation systems.
Data & Network Systems
Design and installation of a structured data network to support reliable connectivity and future operational requirements.
Security & Access Control
Full installation of integrated security systems, including door access control, CCTV, and intruder alarm systems.
Challenges Presented
As the installation was intended to be a showcase for the client’s head office, the project required a non-standard installation sequence, with different trades working in an altered order to typical practice. This demanded close collaboration, regular coordination meetings, and precise workmanship to maintain progress and quality—all while meeting a fixed project deadline.
Solutions Implemented
The solution for this project centred on close collaboration with the client from the outset. Regular meetings were held to review drawings and fully understand their vision, both for day-to-day functionality and the visual impact of the space. On-site, consistent coordination meetings and close cooperation between all trades ensured smooth progress, allowing the team to deliver a high-quality installation that met both operational and aesthetic requirements.
This project was one of our most challenging yet impressive to date. While our installations are always completed to a high standard, they are often hidden behind walls, ceilings, or fittings. In this case, however, the entire installation was fully on display, allowing the quality, precision, and attention to detail of our work to be clearly showcased—highlighting the skill and capability of our team.